PMIPMI
PMP · Question #577
PMP Question #577: Real Exam Question with Answer & Explanation
Sign in or unlock PMP to reveal the answer and full explanation for question #577. The question stem and answer options stay visible for context.
Submitted by marco_it· Apr 18, 2026People
Question
A project is starting its sixth iteration out seven. During the daily meeting, a team member explains that a key function will take longer to complete than originally anticipated. What should the project manager do?
Options
- AAsk for help to increase the team capacity to deliver on time.
- BAsk for a project extension to deliver the committed scope.
- CUpdate the issue log and escalate the problem to the project sponsor.
- DReview the options and possible solutions with the project team.
Unlock PMP to see the answer
You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Agile principles#Team collaboration#Problem solving#Iteration management