PMP · Question #547
An agile project for a database migration impacts nearly all business units of the corporation. Every effort has been made to complete the migration before the end-of-support date for the database…
The correct answer is D. Remove low-value items from the backlog to compensate for the higher cost. Faced with an impediment causing significant delays and increased costs in an agile project, the product owner should remove low-value items from the backlog to offset the higher cost.
Question
An agile project for a database migration impacts nearly all business units of the corporation. Every effort has been made to complete the migration before the end-of-support date for the database platform. A new impediment now implies the need to continue use of the old platform another year at a higher support price. What should the product owner do about this situation?
Options
- AReprioritize the backlog based on value and cost of delay divided by duration.
- BSwitch to a predictive approach to prevent any further delays to completion.
- CReprioritize the backlog based on story size and competence availability.
- DRemove low-value items from the backlog to compensate for the higher cost.
How the community answered
(33 responses)- A9% (3)
- B6% (2)
- C24% (8)
- D61% (20)
Why each option
Faced with an impediment causing significant delays and increased costs in an agile project, the product owner should remove low-value items from the backlog to offset the higher cost.
While reprioritization based on value and cost of delay is an agile practice, simply reordering may not be sufficient to directly address and 'compensate' for a substantial increase in overall project cost.
Switching from an agile to a predictive approach is a significant shift that introduces its own complexities and risks, contradicting agile principles of adaptability rather than resolving the immediate impediment efficiently.
Reprioritizing based on story size and competence helps optimize sprint planning, but it does not directly address or mitigate the financial impact of higher support costs or the need for cost compensation.
The product owner is responsible for maximizing product value and managing the backlog. By removing lower-value items, the project's scope is reduced, which helps compensate for increased costs and delays, ensuring that the remaining, higher-priority features can still be delivered within acceptable constraints.
Concept tested: Product owner's role in backlog and cost management
Source: https://www.scrum.org/resources/what-is-a-product-owner