PMIPMI
PMP · Question #539
PMP Question #539: Real Exam Question with Answer & Explanation
Sign in or unlock PMP to reveal the answer and full explanation for question #539. The question stem and answer options stay visible for context.
Submitted by tom_us· Apr 18, 2026Process
Question
A project stakeholder complained that they did not receive an important delivery that was stated in the schedule. The team member responsible for this deliverable explained that they sent an email to the stakeholder, advising them that the deliverable would not be delivered on time. What should the project manager have done to avoid this situation?
Options
- AConfirmed that the stakeholder was made aware of the delivery delay.
- BCommunicated with the stakeholder directly regarding the delivery delay.
- CTold the team member to send the unfinished deliverable to the stakeholder and finalize it later.
- DEnsured that the team member did not communicate directly with the project stakeholder.
Unlock PMP to see the answer
You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Communication Management#Stakeholder Communication#Confirmation of Communication#Issue Prevention