nerdexam
PMIPMI

PMP · Question #538

PMP Question #538: Real Exam Question with Answer & Explanation

Sign in or unlock PMP to reveal the answer and full explanation for question #538. The question stem and answer options stay visible for context.

Submitted by hassan_iq· Apr 18, 2026Process

Question

An agile team is in the early phases of the development cycle for a project; however, they have already begun to deliver functionality to the customer. The team has identified risks to the project and are working on developing the mitigation strategy. What should the project manager do next?

Options

  • AEscalate the risk to the project sponsor and steering committee.
  • BImplement the risk mitigation strategy according to the highest impact.
  • CIncorporate and prioritize the risks in the risk register according to impact.
  • DDetermine if any of the new risks have any financial impact.

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Risk Management#Risk Register#Risk Prioritization#Agile Risk Management
Full PMP PracticeBrowse All PMP Questions