PMP · Question #503
PMP Question #503: Real Exam Question with Answer & Explanation
Sign in or unlock PMP to reveal the answer and full explanation for question #503. The question stem and answer options stay visible for context.
Question
While reviewing prototypes, the quality team found some deviations that do not affect the mam functionality but have the potential to be an issue in the future. To avoid major problems in the future, the team recommends corrective actions that will require additional funds. The project is already struggling to stay on budget and has even used some of the contingency reserves. What should the project manager do?
Options
- AAsk the product designer why the deviation was not considered in the design phase
- BReport to the project sponsor that the product is working and the project is struggling with the
- CEvaluate and initiate the change request process with the stakeholders
- DAsk the quality team to discard the sample and test again with a new sample
Unlock PMP to see the answer
You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.