PMIPMI
PMP · Question #480
PMP Question #480: Real Exam Question with Answer & Explanation
Sign in or unlock PMP to reveal the answer and full explanation for question #480. The question stem and answer options stay visible for context.
Submitted by deeparc· Apr 18, 2026Process
Question
A project manager is having difficulty acquiring final acceptance of some deliverables from a stakeholder for reasons that seem to be outside of the project acceptance criteria. What should the project manager do?
Options
- APersuade this stakeholder using emotional intelligence skills to obtain acceptance.
- BObtain final acceptance from another stakeholder who is also familiar with the project.
- CEscalate this issue to the project sponsor and ask for support in obtaining final stakeholder
- DCreate a project acceptance waiver noting the stakeholder's concerns so they can be addressed
Unlock PMP to see the answer
You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Stakeholder management#Issue escalation#Acceptance criteria#Project governance