PMP · Question #479
PMP Question #479: Real Exam Question with Answer & Explanation
Sign in or unlock PMP to reveal the answer and full explanation for question #479. The question stem and answer options stay visible for context.
Question
In a hybrid project, the customer decided on a major change for the project design. This change was approved and the impact on schedule and budget is known. The software team leader, who is supposed to develop the software, refuses to commit to delivery dates claiming that they work using an agile approach and cannot commit to a final delivery date. The hardware team depends on this software to develop their part of the product. What should the project manager do?
Options
- AAdd this risk to the risk register and monitor it according to the risk management plan
- BEscalate this to higher management and ask for help to resolve the issue
- CImpose the delivery dates on the software team leader and notify the functional manager about
- DAsk the software team leader to use a predictive approach and commit to a delivery date