nerdexam
PMIPMI

PMP · Question #479

PMP Question #479: Real Exam Question with Answer & Explanation

Sign in or unlock PMP to reveal the answer and full explanation for question #479. The question stem and answer options stay visible for context.

Submitted by akirajp· Apr 18, 2026Process

Question

In a hybrid project, the customer decided on a major change for the project design. This change was approved and the impact on schedule and budget is known. The software team leader, who is supposed to develop the software, refuses to commit to delivery dates claiming that they work using an agile approach and cannot commit to a final delivery date. The hardware team depends on this software to develop their part of the product. What should the project manager do?

Options

  • AAdd this risk to the risk register and monitor it according to the risk management plan
  • BEscalate this to higher management and ask for help to resolve the issue
  • CImpose the delivery dates on the software team leader and notify the functional manager about
  • DAsk the software team leader to use a predictive approach and commit to a delivery date

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Risk Management#Hybrid Project Management#Team Dynamics#Dependency Management
Full PMP PracticeBrowse All PMP Questions