PMP · Question #466
Early in the execution phase, a project manager discovers that recent changes in enterprise environmental factors (EEFs) will severely reduce the implementation cost and shorten the project schedule.
The correct answer is D. Follow the project escalation policy and communications management plan. When significant positive changes to cost and schedule occur due to EEFs, the project manager must follow the established project escalation policy and communications management plan. This ensures proper review, approval, and communication of the project baseline changes to all r
Question
Early in the execution phase, a project manager discovers that recent changes in enterprise environmental factors (EEFs) will severely reduce the implementation cost and shorten the project schedule. How should the project manager address this situation?
Options
- AMeet with the project team to decide how the remaining budget will be spent
- BKeep the extra budget as management reserve until project closeout
- CGive the team extra time to finish tasks within the original timeline
- DFollow the project escalation policy and communications management plan
How the community answered
(26 responses)- A12% (3)
- B4% (1)
- C4% (1)
- D81% (21)
Why each option
When significant positive changes to cost and schedule occur due to EEFs, the project manager must follow the established project escalation policy and communications management plan. This ensures proper review, approval, and communication of the project baseline changes to all relevant stakeholders.
Deciding how to spend "extra" budget without formal approval is a breach of financial control and project governance.
Keeping extra budget as management reserve without communicating the improved project outlook misrepresents the project status and is not transparent.
Giving the team extra time when the schedule can be shortened means deliberately slowing down the project, which is not in the best interest of the business.
Significant changes, even positive ones like reduced cost and shortened schedule, represent a deviation from the approved baseline. The project manager must adhere to formal project governance, which includes following the established escalation policy and communications management plan to notify appropriate stakeholders and seek formal approval for baseline adjustments.
Concept tested: Project governance, change management, EEFs
Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok
Topics
Community Discussion
10D is correct. Think of it like a delivery driver finding out a road closure just opened up ahead: you don't just floor it and pocket the gas money, you call dispatch to report the change and follow company protocol. EEF changes are outside the PM's authority to resolve unilaterally, so you follow the escalation policy and communications management plan to keep stakeholders informed.
Good analogy on the escalation part but EEF changes that open up like your road closure example actually flow through Monitor and Control Project Work into change control, not just comms, since an approved change request is what lets you actually act on the new opportunity.
Got D on my exam last week. EEF change means escalate per comms plan.
Agreed on D, but make a flashcard that distinguishes EEF changes from OPAs, since people blur them and the exam loves that trap.
D is correct because EEF changes that affect cost baseline and schedule are outside the PMs authority and must be escalated per the communications management plan. For a flashcard, the trigger here is enterprise environmental factors changing, which deserves a card with a one-week interval since people reflexively pick A when they see budget questions. One thing I am still parsing, does the escalation policy get invoked any time EEFs shift, or only when the change impacts baselines?
Good catch on D, and to answer your question, EEFs shift all the time without triggering escalation, like when a team gets a new tool or a policy updates, but it only goes up the chain when the shift actually impacts a baseline or a constraint you are held to.
Sat for PMP three weeks ago and A was my first instinct since it sounds like the right thing to do. Re-read the stem though, EEF changes that impact cost and schedule this significantly mean you follow the escalation policy and comms plan, which is exactly D.
D is the right call, and the quick way to remember it is that EEFs are like the weather: you cannot control them, you can only grab your umbrella and report the flooding to the boss, which is exactly what the escalation path does.
Going with C here. If the EEF change makes things cheaper and faster, the team gets breathing room to deliver within the original timeline with higher quality, which is a win for everyone.
D is correct here because an EEF change that impacts cost or schedule triggers the Monitor and Control Project Work process, which then feeds into the Perform Integrated Change Control process. C skips that step, and you never just absorb a change without running it through change control, even when it seems like a win.