PMIPMI
PMP · Question #466
PMP Question #466: Real Exam Question with Answer & Explanation
Sign in or unlock PMP to reveal the answer and full explanation for question #466. The question stem and answer options stay visible for context.
Submitted by lars.no· Apr 18, 2026Process
Question
Early in the execution phase, a project manager discovers that recent changes in enterprise environmental factors (EEFs) will severely reduce the implementation cost and shorten the project schedule. How should the project manager address this situation?
Options
- AMeet with the project team to decide how the remaining budget will be spent
- BKeep the extra budget as management reserve until project closeout
- CGive the team extra time to finish tasks within the original timeline
- DFollow the project escalation policy and communications management plan
Unlock PMP to see the answer
You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Change Management#Communications Management#Escalation Procedures#Project Governance