A group has been working together for one month. During daily meetings a team member continues to express issues in completing their tasks. What should the project manager do?

Options

  • AWait for the team to identify and solve the problem independently
  • BMove the team member to another task that is more skill appropriate
  • CHave a confidential discussion with the team member to identify the root cause
  • DStart a discussion with all team members to help resolve the issues

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Team performance#Coaching#Conflict management#Communication
Full PMP PracticeBrowse All PMP Questions