PMIPMI
PMP · Question #454
PMP Question #454: Real Exam Question with Answer & Explanation
Sign in or unlock PMP to reveal the answer and full explanation for question #454. The question stem and answer options stay visible for context.
Submitted by lucia.co· Apr 18, 2026Business Environment
Question
A project manager realizes that a project is becoming delayed because some key decisions are affected by contradicting views between the organization's senior management and external stakeholders. What should the project manager do?
Options
- AReview the stakeholder register and ensure that communications are being followed in line with
- BIsolate the project team from external factors such as senior management and stakeholders so
- CReview the remaining scope and rebaseline the project's schedule to take into account delays in
- DReview the adequacy of the project's governance and ensure that an appropriate structure is in
Unlock PMP to see the answer
You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Project Governance#Stakeholder Management#Strategic Decision Making#Conflict Resolution