PMI
PMP · Question #452
A project manager has two projects that are being executed at the same time. The duration of the critical project must be reduced, but the project manager does not have enough resources to achieve thi
Sign in or unlock PMP to reveal the answer and full explanation for question #452. The question stem and answer options stay visible for context.
Submitted by tarun92· Apr 18, 2026Process
Question
A project manager has two projects that are being executed at the same time. The duration of the critical project must be reduced, but the project manager does not have enough resources to achieve this goal. In addition, the schedule does not have activities that can be overlapped. What should the project manager do?
Options
- AAnalyze both projects to determine the most effective use of common resources
- BUse resource optimization to justify requesting more resources for the critical project
- CProvide schedule optimization training to the project teams to improve their skills
- DApply fast-tracking techniques to compress the schedule of the critical project
Unlock PMP to see the answer
You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Resource Management#Multi-project Management#Schedule Compression#Resource Optimization