Question
A project in the execution phase is behind schedule and is missing some materials. The contractor submits an offer to supply the missing materials and reimburse the cost since the internal procurement process will cause more delay. The project manager does not agree with the costs submitted by the contractor for the missing materials. What should the project manager do next?
Options
- AAsk the project sponsor to allocate more budget to cover the costs
- BUpdate the procurement management plan and negotiate with the contractor.
- CAsk the contractor to review the offer and reduce the costs.
- DUpdate the procurement strategy and negotiate with the contractor