nerdexam
PMIPMI

PMP · Question #428

PMP Question #428: Real Exam Question with Answer & Explanation

Sign in or unlock PMP to reveal the answer and full explanation for question #428. The question stem and answer options stay visible for context.

Submitted by fatima_kr· Apr 18, 2026People

Question

A project manager presented the project schedule to the mam stakeholders. They have requested that the project be completed two months earlier than the scheduled date. What should the project manager do?

Options

  • AHold a stakeholder meeting to align timelines and scope expectations
  • BCrash the schedule to shorten the timeline while keeping the scope unchanged
  • CUpdate the cost management plan to allocate more resources to the project to finish the scope
  • DReduce the scope of the project by removing activities and shortening the timeline

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Stakeholder Management#Change Management#Schedule Management#Project Constraints
Full PMP PracticeBrowse All PMP Questions