nerdexam
PMI

PMP · Question #421

After gathering all the requirements for a project with dependencies on external stakeholders, the project team is finishing the second iteration. At this point, the project manager learns about a pos

The correct answer is C. Review target benefits. When a potential regulatory change threatens product launch, the project manager should review target benefits to understand the impact and re-evaluate project viability. This helps determine if the project still aligns with its original goals or if adjustments are needed to achi

Submitted by certguy· Apr 18, 2026Business Environment

Question

After gathering all the requirements for a project with dependencies on external stakeholders, the project team is finishing the second iteration. At this point, the project manager learns about a possible change in regulations that would prevent the product launch. What should the project manager do to realize benefits?

Options

  • AAdd an entry in the risk log
  • BImplement the changes
  • CReview target benefits
  • DImprove the team's velocity

How the community answered

(55 responses)
  • A
    4% (2)
  • B
    5% (3)
  • C
    80% (44)
  • D
    11% (6)

Why each option

When a potential regulatory change threatens product launch, the project manager should review target benefits to understand the impact and re-evaluate project viability. This helps determine if the project still aligns with its original goals or if adjustments are needed to achieve value.

AAdd an entry in the risk log

Adding an entry to the risk log is a step in risk management, but it doesn't directly address how to realize benefits in the face of a potential show-stopping regulatory change; it's a reactive tracking measure.

BImplement the changes

Implementing changes is premature and potentially costly without first understanding the full impact of the regulatory change on the project's benefits and verifying the necessity and nature of those changes.

CReview target benefitsCorrect

A potential change in regulations that could prevent product launch directly impacts the project's ability to deliver its intended value and benefits. Reviewing target benefits allows the project manager to assess if the project's original goals are still achievable, if the expected value needs to be re-evaluated, or if the project scope and strategy must be adjusted to align with the new regulatory landscape and realize any possible benefits.

DImprove the team's velocity

Improving team velocity addresses efficiency in delivery but does not resolve a fundamental external regulatory issue that could prevent product launch and benefit realization.

Concept tested: Project benefits management and risk impact assessment

Source: https://www.pmi.org/pmbok-guide-standards/benefits-management

Topics

#Benefits Realization#Risk Management#Business Value#Regulatory Compliance

Community Discussion

No community discussion yet for this question.

Full PMP Practice