PMP · Question #377

PMP Question #377: Real Exam Question with Answer & Explanation

Sign in or unlock PMP to reveal the answer and full explanation for question #377. The question stem and answer options stay visible for context.

Submitted by krish.m· Apr 18, 2026Process

Question

The resource management plan is already done, and the team is located in different countries around the world. Team members are in multiple time zones, and they use different languages for communication. The project manager needs to keep the team organized and avoid misunderstandings and miscommunication that may produce a negative impact to the project. What should the project manager do to reduce negative impacts to the project?

Options

  • AModify the communications management plan to account for regional differences
  • BConduct cultural awareness seminars
  • CHold a virtual meeting to discuss the political environment
  • DConduct a multigenerational management training session

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Communications Management#Distributed Teams#Cross-cultural Communication#Project Planning