PMI
PMP · Question #358
A project sponsor commonly asks the project manager to skip project retrospectives due to time constraints. However, the project manager persists in running this critical ceremony by reducing the time
Sign in or unlock PMP to reveal the answer and full explanation for question #358. The question stem and answer options stay visible for context.
Submitted by kim_seoul· Apr 18, 2026Process
Question
A project sponsor commonly asks the project manager to skip project retrospectives due to time constraints. However, the project manager persists in running this critical ceremony by reducing the time for preparation and for discussion. What are two issues that these actions by the project manager could cause? (Choose two.)
Options
- AA lot of discussions that yield no results or possibly too many results
- BA lack of direction and motivation for the team in the workshop
- CLessons learned from other teams to not be considered
- DTime management plan for the retrospective workshop to not be updated
- EA focus on the negative and a disinterest in further improvements
Unlock PMP to see the answer
You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Project Retrospective#Lessons Learned#Process Improvement#Meeting Management