PMIPMI
PMP · Question #329
PMP Question #329: Real Exam Question with Answer & Explanation
Sign in or unlock PMP to reveal the answer and full explanation for question #329. The question stem and answer options stay visible for context.
Submitted by kavita_s· Apr 18, 2026Process
Question
The project is delayed due to the high amount of major changes requested by different stakeholders at different stages of the project. If the project continues on the same path, it will consume twice the time and budget planned. What two actions can the project manager take to be more cost effective? (Choose two.)
Options
- AConduct a stakeholder analysis
- BReinforce team communication.
- CUpdate the project management plan with the new timeline
- DAdopt an incremental approach
- ELeverage work between team members
Unlock PMP to see the answer
You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Change Management#Stakeholder Management#Project Lifecycle#Cost Effectiveness