PMIPMI
PMP · Question #299
PMP Question #299: Real Exam Question with Answer & Explanation
Sign in or unlock PMP to reveal the answer and full explanation for question #299. The question stem and answer options stay visible for context.
Submitted by javi_es· Apr 18, 2026Process
Question
During the implementation of a project, the project team discovered a new opportunity. After an internal review, the project team agreed that the opportunity is outside of the project scope. The project manager decided to update the risk register and escalate the opportunity to a higher level. What should the project manager do next with this opportunity?
Options
- ANo more action is required.
- BShare this opportunity with another project.
- CFurther monitor the opportunity.
- DEstablish a contingency reserve to support the opportunity.
Unlock PMP to see the answer
You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Opportunity management#Scope management#Escalation process#Project manager's responsibility