PMP · Question #300
PMP Question #300: Real Exam Question with Answer & Explanation
Sign in or unlock PMP to reveal the answer and full explanation for question #300. The question stem and answer options stay visible for context.
Submitted by katya_ua· Apr 18, 2026People
Question
During a project's third iteration, two of the existing team members were replaced. As the project entered the next iteration, the team velocity dropped and the performance started to slip. What should the project manager do?
Options
- AGuide the team to revert back to the forming and storming stages.
- BDiscuss the decrease in productivity with human resources (HR).
- CConvene a team building event to address key performance indicators (KPIs).
- DEscalate the issue to the project sponsor.
Unlock PMP to see the answer
You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Team Development#Tuckman's Stages#Team Dynamics#Agile Team Management