A project manager joins a team that is providing a customized enterprise resource planning (ERP) system to a client. A potential design problem is identified by the development team. After reviewing this issue with the project owner and team members, all agreed to revise the design to avoid a system defect when deployed. The design is already approved. What should be the project manager's next steps?
Options
- AMake a change request and get formal approval from the project owner.
- BInform the client of the problem and follow the change request process.
- CConduct a proof of concept to make sure there are no problems in the revised design.
- DAmend the design specifications and pass them to the development team for reprogramming.