PMP · Question #295

A project manager joins a team that is providing a customized enterprise resource planning (ERP) system to a client. A potential design problem is identified by the development team. After reviewing t

The correct answer is C. Conduct a proof of concept to make sure there are no problems in the revised design.. After agreeing to revise an already approved design to prevent a defect, the project manager's next crucial step is to conduct a proof of concept. This validates the revised design to ensure it effectively solves the problem without introducing new issues before full implementati

Submitted by carlos_mx· Apr 18, 2026Process

Question

A project manager joins a team that is providing a customized enterprise resource planning (ERP) system to a client. A potential design problem is identified by the development team. After reviewing this issue with the project owner and team members, all agreed to revise the design to avoid a system defect when deployed. The design is already approved. What should be the project manager's next steps?

Options

  • AMake a change request and get formal approval from the project owner.
  • BInform the client of the problem and follow the change request process.
  • CConduct a proof of concept to make sure there are no problems in the revised design.
  • DAmend the design specifications and pass them to the development team for reprogramming.

How the community answered

(57 responses)
  • A
    4% (2)
  • B
    16% (9)
  • C
    72% (41)
  • D
    9% (5)

Why each option

After agreeing to revise an already approved design to prevent a defect, the project manager's next crucial step is to conduct a proof of concept. This validates the revised design to ensure it effectively solves the problem without introducing new issues before full implementation.

AMake a change request and get formal approval from the project owner.

While a change request will eventually be needed for the approved design, it is premature to make one before ensuring the revised design itself is sound and effective.

BInform the client of the problem and follow the change request process.

Informing the client and following the change request process is necessary, but validating the revised design first ensures the proposed solution is robust before presenting it.

CConduct a proof of concept to make sure there are no problems in the revised design.Correct

Conducting a proof of concept (PoC) for the revised design is essential to validate that the changes effectively resolve the identified potential problem without introducing new defects or unforeseen issues. Since the original design was already approved and this is a significant revision, validating the new approach minimizes risk before proceeding with full implementation and formal change processes.

DAmend the design specifications and pass them to the development team for reprogramming.

Amending specifications and passing them to development without validating the revised design increases the risk of building an unproven solution that might still have defects.

Concept tested: Design validation and risk mitigation

Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok/project-risk-management

Topics

#Change Management#Risk Management#Quality Assurance#Project Validation