nerdexam
PMIPMI

PMP · Question #27

PMP Question #27: Real Exam Question with Answer & Explanation

Sign in or unlock PMP to reveal the answer and full explanation for question #27. The question stem and answer options stay visible for context.

Submitted by tyler.j· Apr 18, 2026Process

Question

A project team is implementing an enterprise notification tool with a vendor. The project manager noticed that this vendor's developer has been reporting the same status for several weeks in a row. A few days later, the vendor communicates that the deliverable will not be completed on time due to resource constraints within their company. What should the project manager do next?

Options

  • AUpdate the risk register to reflect the delay, communicate the impact to the schedule, and
  • BConduct a project review with the project sponsor to explain the delay and add a developer to
  • CAdd the delay to the issue log and work with the vendor for a resolution that will bring the
  • DReview the contract with the vendor to go over the financial penalty that is applicable to this

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Issue Management#Vendor Management#Problem Resolution#Project Monitoring
Full PMP PracticeBrowse All PMP Questions