PMP · Question #237
A project is ready to deliver the first batch of the product when a quality control check rejects the product as unfit for delivery. The root cause analysis (RCA) shows that a component added as part
The correct answer is B. Review the quality management process and perform a process audit as part of ongoing quality. After a critical quality failure due to insufficient testing of a new component, the project manager should review the quality management process and conduct a process audit to identify systemic weaknesses.
Question
A project is ready to deliver the first batch of the product when a quality control check rejects the product as unfit for delivery. The root cause analysis (RCA) shows that a component added as part of the latest change request was not tested throughout the development cycle. What should the project manager do next?
Options
- AReview the change control process to ensure quality management artifacts are updated as part of
- BReview the quality management process and perform a process audit as part of ongoing quality
- CReview the communications management plan to ensure change requests are communicated to
- DReview the quality management process with the project management office (PMO) to ensure
How the community answered
(32 responses)- A6% (2)
- B81% (26)
- C3% (1)
- D9% (3)
Why each option
After a critical quality failure due to insufficient testing of a new component, the project manager should review the quality management process and conduct a process audit to identify systemic weaknesses.
Reviewing the change control process specifically for "quality management artifacts" is too narrow; the problem stems from the application of quality management to the changed component, not just documentation.
The root cause analysis clearly points to a failure in the testing aspect of quality management for a new component. Therefore, the most appropriate next step is to systematically review the existing quality management process and perform an audit to understand why this oversight occurred, identifying process gaps or non-compliance to prevent recurrence.
While communication is important, the RCA specifically states the component "was not tested throughout the development cycle," indicating a process failure in quality assurance, not primarily a communication breakdown.
Reviewing the quality management process with the PMO might be a later step, but the immediate action is for the project manager to review and audit the process within the project context to understand the failure before escalating or seeking external review.
Concept tested: Quality management process audit and improvement
Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok