nerdexam
PMIPMI

PMP · Question #236

PMP Question #236: Real Exam Question with Answer & Explanation

Sign in or unlock PMP to reveal the answer and full explanation for question #236. The question stem and answer options stay visible for context.

Submitted by daniela_cl· Apr 18, 2026Process

Question

In the past year, a company paid US$60,000 to an external subcontractor for an ongoing project. The project manager has been asked to evaluate if the project can be delivered more cost effectively this year by using internal labor. The project manager used an optimistic term of 4 months, a pessimistic term of 6 months, and a most expected term of 5 months, and has concluded that the service can be delivered with the following resources: - Two engineers (monthly salary of US$700 each) - One project manager (monthly salary of US$1,600) - Additional estimated monthly expenses of US$2,000 The project manager used the program evaluation and review technique (PERT) to calculate the savings if the project is delivered with in-house resources. How much money will the project manager estimate the company can save?

Options

  • AUS$35,000
  • BUS$20,000
  • CUS$40,000
  • DUS$30,000

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Cost Management#PERT#Make-or-Buy Analysis#Project Estimation
Full PMP PracticeBrowse All PMP Questions