PMP · Question #225

PMP Question #225: Real Exam Question with Answer & Explanation

Sign in or unlock PMP to reveal the answer and full explanation for question #225. The question stem and answer options stay visible for context.

Submitted by yasin.bd· Apr 18, 2026Process

Question

A vendor has manufactured a complex product. During a factory acceptance test, several deficiencies were identified. Product delivery is on the critical path, and any delay would impact project completion. What should the project manager do?

Options

  • AInitiate regular conference calls with the vendor for status updates to keep this item in focus.
  • BHold the shipment until the rework is completed at the vendor's facility to eliminate extra work on-
  • CAssess the schedule impact and evaluate the most feasible solution to keep the project on track.
  • DShip the package as is, complete carryover work on-site, and back charge the vendor for the

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Critical Path Management#Problem Solving#Quality Management#Schedule Management