PMP · Question #208
PMP Question #208: Real Exam Question with Answer & Explanation
Sign in or unlock PMP to reveal the answer and full explanation for question #208. The question stem and answer options stay visible for context.
Submitted by paula_co· Apr 18, 2026Process
Question
In the daily check-in meeting, a team member informs the project team that the licenses for one of the components that will be used will expire in a couple of months. The licensing cost is significant. What should the project manager do next?
Options
- AEvaluate the impact of nonrenewal of the license.
- BEscalate the licensing issue to the product owner.
- CAdd a spike to the backlog for an alternative design.
- DRaise a change request to secure the renewal.
Unlock PMP to see the answer
You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Risk Management#Issue Management#Problem Solving