Question
A project manager leads a development project for a mobile chatting application. One of the experienced developers constantly creates conflicts with the other team members. As a result, the other team members are refusing to work with the developer. Since the developer is a high performer, the project goals may be negatively impacted if they leave the team. What should the project manager do in this situation?
Options
- AMeet with the developer and ask them to be respectful with the other team members and work
- BMeet with the team members and developer individually to understand the situation and build an
- CCollect the team's feedback and send it to human resources (HR) to resolve the conflict.
- DArrange a team-building training session and require all of the team members to attend.