nerdexam
PMIPMI

PMP · Question #205

PMP Question #205: Real Exam Question with Answer & Explanation

Sign in or unlock PMP to reveal the answer and full explanation for question #205. The question stem and answer options stay visible for context.

Submitted by jordan8· Apr 18, 2026Process

Question

An agile team has completed five sprints. The final product is expected to be delivered in another three sprints. The project manager receives a call from the technical resource manager that one of the developers must take leave for the next 4 weeks, with no temporary replacement available. This is going to significantly impact the deliverable. What should the project manager do?

Options

  • ARequest additional funding from the sponsor to obtain a new resource to fill in the gap.
  • BInform the customer of the impact immediately and prepare for escalation.
  • CAsk the product owner to stretch the delivery team further to complete the final product in the
  • DPerform an impact analysis, readjust the schedule as needed, and communicate the changes to

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Issue Management#Change Management#Stakeholder Communication#Agile Adaptation
Full PMP PracticeBrowse All PMP Questions