Question
An agile team has completed five sprints. The final product is expected to be delivered in another three sprints. The project manager receives a call from the technical resource manager that one of the developers must take leave for the next 4 weeks, with no temporary replacement available. This is going to significantly impact the deliverable. What should the project manager do?
Options
- ARequest additional funding from the sponsor to obtain a new resource to fill in the gap.
- BInform the customer of the impact immediately and prepare for escalation.
- CAsk the product owner to stretch the delivery team further to complete the final product in the
- DPerform an impact analysis, readjust the schedule as needed, and communicate the changes to