PMP · Question #204
PMP Question #204: Real Exam Question with Answer & Explanation
Sign in or unlock PMP to reveal the answer and full explanation for question #204. The question stem and answer options stay visible for context.
Question
An agile team is working on a 2-week sprint to deliver business value. About 1 week after the sprint starts, the team members do not feel confident about the product increment they are building. They do not want to wait until the end of the sprint and want to validate the product increment with the product owner now. What should the project manager do to mitigate this risk?
Options
- AExtend the sprint end date in anticipation of feedback from the product owner that will require
- BSchedule an additional interim demo with the product owner.
- CAddress the issue as part of the retrospective.
- DAsk the team to work overtime toward the end of the sprint to meet the original sprint end date.
Unlock PMP to see the answer
You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.