PMIPMI
PMP · Question #1437
PMP Question #1437: Real Exam Question with Answer & Explanation
Sign in or unlock PMP to reveal the answer and full explanation for question #1437. The question stem and answer options stay visible for context.
Submitted by anna_se· Apr 18, 2026Process
Question
A project requires testing of the final product to be done at another department's testing facility, which is known for having low availability. This situation could potentially impact the project schedule. What should the project manager do next?
Options
- AUpdate the project schedule.
- BUpdate the issue log.
- CUpdate the lessons learned register.
- DUpdate the risk register.
Unlock PMP to see the answer
You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Risk Management#Risk Identification#Project Artifacts#Risk Register