PMIPMI
PMP · Question #1438
PMP Question #1438: Real Exam Question with Answer & Explanation
Sign in or unlock PMP to reveal the answer and full explanation for question #1438. The question stem and answer options stay visible for context.
Submitted by eva_at· Apr 18, 2026People
Question
Due to unforeseen circumstances, a contractor was unable to mobilize the project team, which was necessary to conduct face-to-face meetings and discussions. Virtual meetings were subsequently put in place, but the local project team and end users now face a communication gap that is causing the team's low performance. What should the project manager do?
Options
- AAsk the contractor to solve this problem because this is a contractual obligation.
- BTerminate the contract and initiate a new one with a local contractor.
- CReassess continually to remove blockers for the team.
- DImplement key performance indicators (KPIs) and convince the contractor to engage the team.
Unlock PMP to see the answer
You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Team Performance#Communication Barriers#Impediment Resolution#Adaptive Practices