PMIPMI
PMP · Question #1420
PMP Question #1420: Real Exam Question with Answer & Explanation
Sign in or unlock PMP to reveal the answer and full explanation for question #1420. The question stem and answer options stay visible for context.
Submitted by katya_ua· Apr 18, 2026Process
Question
A project team member raised a risk that the threat of country-wide power cuts may affect the project time line for a software development project. In the last month, this risk materialized and the project time line had to be extended by 2 months. Which two actions should the project manager take? (Choose two.)
Options
- AAsk the team member to work overtime to make up the lime lost so that the project schedule is
- BLog it in the risk register and work with the relevant owner to implement the mitigation action plan.
- CAnalyze the impact of the issue and submit a change request to update the project schedule.
- DInform the project sponsor that the risk has materialized and request that the project budget be
- EExtend the project deadline and update the project schedule to reflect the delay.
Unlock PMP to see the answer
You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Risk Management#Issue Management#Change Control#Schedule Management