nerdexam
PMIPMI

PMP · Question #1412

PMP Question #1412: Real Exam Question with Answer & Explanation

Sign in or unlock PMP to reveal the answer and full explanation for question #1412. The question stem and answer options stay visible for context.

Submitted by kavita_s· Apr 18, 2026Process

Question

After a project status meeting, the project manager realizes that the project is under budget, quality checks are positive, and the schedule variance is negative. How should the project manager qualify the project status?

Options

  • AAhead of schedule
  • BOn schedule
  • CBehind schedule
  • DStopped

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Schedule Variance#Earned Value Management#Project Performance#Monitoring and Controlling
Full PMP PracticeBrowse All PMP Questions