PMP · Question #1404
PMP Question #1404: Real Exam Question with Answer & Explanation
Sign in or unlock PMP to reveal the answer and full explanation for question #1404. The question stem and answer options stay visible for context.
Question
A project manager is working on a software development project. The project manager and the project team identified the project risks. As the project progressed one of the risks materialized and the project manager referred to the risk management plan to determine how to manage the risk. Once the risk management strategy was chosen and implemented the risk was closed. At what point did the project manager move the risk from the risk register to the issue log?
Options
- ARisk occurred
- BRisk monitored
- CRisk managed
- DRisk identified
Unlock PMP to see the answer
You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.