nerdexam
PMIPMI

PMP · Question #1368

PMP Question #1368: Real Exam Question with Answer & Explanation

The correct answer is D: Schedule regular project audits.. A project requires adherence to defined cybersecurity compliance for a customer project.

Submitted by kim_seoul· Apr 18, 2026Process

Question

A team needs to follow defined cybersecurity compliance that is mandatory for a customer project. What should the project manager do to monitor compliance in the project?

Options

  • AConfer with team members.
  • BDiscuss with the customer.
  • CReview with security experts.
  • DSchedule regular project audits.

Explanation

A project requires adherence to defined cybersecurity compliance for a customer project.

Common mistakes.

  • A. Conferring with team members is good for ongoing communication but does not provide formal, independent verification of compliance.
  • B. Discussing with the customer confirms their expectations but doesn't independently monitor the team's internal adherence to compliance.
  • C. Reviewing with security experts is valuable for guidance and assessment but is typically part of an audit process or a specific expert review, not a continuous monitoring mechanism by itself.

Concept tested. Project compliance monitoring and auditing

Reference. https://www.pmi.org/learning/library/project-management-audit-1250

Topics

#Compliance Monitoring#Project Audits#Monitoring & Controlling#Cybersecurity

Community Discussion

No community discussion yet for this question.

Full PMP PracticeBrowse All PMP Questions