PMIPMI
PMP · Question #1368
PMP Question #1368: Real Exam Question with Answer & Explanation
The correct answer is D: Schedule regular project audits.. A project requires adherence to defined cybersecurity compliance for a customer project.
Submitted by kim_seoul· Apr 18, 2026Process
Question
A team needs to follow defined cybersecurity compliance that is mandatory for a customer project. What should the project manager do to monitor compliance in the project?
Options
- AConfer with team members.
- BDiscuss with the customer.
- CReview with security experts.
- DSchedule regular project audits.
Explanation
A project requires adherence to defined cybersecurity compliance for a customer project.
Common mistakes.
- A. Conferring with team members is good for ongoing communication but does not provide formal, independent verification of compliance.
- B. Discussing with the customer confirms their expectations but doesn't independently monitor the team's internal adherence to compliance.
- C. Reviewing with security experts is valuable for guidance and assessment but is typically part of an audit process or a specific expert review, not a continuous monitoring mechanism by itself.
Concept tested. Project compliance monitoring and auditing
Reference. https://www.pmi.org/learning/library/project-management-audit-1250
Topics
#Compliance Monitoring#Project Audits#Monitoring & Controlling#Cybersecurity
Community Discussion
No community discussion yet for this question.