PMIPMI
PMP · Question #1363
PMP Question #1363: Real Exam Question with Answer & Explanation
The correct answer is D: At the end of each and every iteration. A project team is working in an iterative manner, delivering incremental value.
Submitted by akirajp· Apr 18, 2026Process
Question
A project team is working on a product that is planned for multiple iterations. They are delivering incremental value. When should the value be demonstrated?
Options
- AAfter full development is completed
- BWhen the sponsor approves the increment
- CWhen a major feature is completed
- DAt the end of each and every iteration
Explanation
A project team is working in an iterative manner, delivering incremental value.
Common mistakes.
- A. Waiting until full development is completed contradicts the iterative nature of agile, delaying feedback and the ability to adapt.
- B. While sponsor approval is important, the demonstration of value should happen regularly, not just contingent on a single approval event.
- C. Demonstrating only after a 'major feature' is completed is less frequent than optimal in agile and might still delay feedback compared to end-of-iteration demonstrations.
Concept tested. Agile iterative delivery and sprint review
Reference. https://scrumguides.org/scrum-guide.html#sprint-review
Topics
#Agile#Iterative Development#Incremental Delivery#Value Demonstration
Community Discussion
No community discussion yet for this question.