The correct answer is D: At the end of each and every iteration. A project team is working in an iterative manner, delivering incremental value.

Submitted by akirajp· Apr 18, 2026Process

Question

A project team is working on a product that is planned for multiple iterations. They are delivering incremental value. When should the value be demonstrated?

Options

  • AAfter full development is completed
  • BWhen the sponsor approves the increment
  • CWhen a major feature is completed
  • DAt the end of each and every iteration

Explanation

A project team is working in an iterative manner, delivering incremental value.

Common mistakes.

  • A. Waiting until full development is completed contradicts the iterative nature of agile, delaying feedback and the ability to adapt.
  • B. While sponsor approval is important, the demonstration of value should happen regularly, not just contingent on a single approval event.
  • C. Demonstrating only after a 'major feature' is completed is less frequent than optimal in agile and might still delay feedback compared to end-of-iteration demonstrations.

Concept tested. Agile iterative delivery and sprint review

Reference. https://scrumguides.org/scrum-guide.html#sprint-review

Topics

#Agile#Iterative Development#Incremental Delivery#Value Demonstration