PMP · Question #1362
PMP Question #1362: Real Exam Question with Answer & Explanation
The correct answer is B: Find the root cause of the issue and discuss the customer's current engagement.. The customer is not clearing packages for shipment and is not participating in communication efforts, leading to a bottleneck.
Question
A project involves exporting 150 packages to the customer. However, only 30 packages have been cleared by the customer for shipment. The logistics manager provided details to the customer 2 weeks ago and set up a weekly conference call to effectively communicate with them, but the customer has not been participating in the calls. How should the project manager handle this situation?
Options
- ARequest a change in the contract to include the shipment in the project management plan.
- BFind the root cause of the issue and discuss the customer's current engagement.
- CInform the customer that subsequent packages cannot be manufactured.
- DRequest a delivery date extension from the customer.
Explanation
The customer is not clearing packages for shipment and is not participating in communication efforts, leading to a bottleneck.
Common mistakes.
- A. Requesting a contract change without understanding the root cause is premature and may not address the core issue of customer engagement.
- C. Threatening to stop manufacturing is an adversarial approach that can damage customer relationships and may not be a practical solution to the clearance issue.
- D. Requesting a delivery date extension is a reactive measure that doesn't solve the underlying problem of customer disengagement and package clearance.
Concept tested. Problem-solving and stakeholder engagement