nerdexam
PMIPMI

PMP · Question #1351

PMP Question #1351: Real Exam Question with Answer & Explanation

Sign in or unlock PMP to reveal the answer and full explanation for question #1351. The question stem and answer options stay visible for context.

Submitted by chiamaka_o· Apr 18, 2026Process

Question

A project manager is made aware that there are defects in the parts provided by a supplier, which are causing delays in the testing phase. The supplier claims that all parts have been delivered as per the contract. If the defects are not fixed by the supplier within one week, the product release will be impacted. What should the project manager do?

Options

  • ARequest a cancellation of the procurement contract with the supplier and impose a penalty.
  • BReview the procurement contract and ask the supplier to negotiate a solution.
  • CEscalate this issue to senior management, as the supplier is not following the procurement
  • DRequest a revision of the procurement contract to include specifications for the parts.

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Procurement management#Contract management#Quality assurance#Issue resolution
Full PMP PracticeBrowse All PMP Questions