nerdexam
PMIPMI

PMP · Question #1346

PMP Question #1346: Real Exam Question with Answer & Explanation

Sign in or unlock PMP to reveal the answer and full explanation for question #1346. The question stem and answer options stay visible for context.

Submitted by takeshi77· Apr 18, 2026Business Environment

Question

A project manager has been assigned to a project that is consolidating regional operations into a global operation. The project sponsor explains that some efficiencies could be obtained from this unification. However, the sponsor is not sure if this effort will have a return on investment (ROI) and would like the project manager's opinion. What should the project manager do?

Options

  • ARequest the project sponsor to include a commitment from the stakeholders to reduce costs
  • BSuggest conducting a detailed cost-benefit analysis for financial feasibility before the start of the
  • CRecommend conducting an initial high-level feasibility assessment to estimate the cost and
  • DExplain that the project manager is limited to demonstrating earned value (EV) from the project

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Project Initiation#Feasibility Study#Cost-Benefit Analysis#ROI Assessment
Full PMP PracticeBrowse All PMP Questions