nerdexam
PMIPMI

PMP · Question #1332

PMP Question #1332: Real Exam Question with Answer & Explanation

Sign in or unlock PMP to reveal the answer and full explanation for question #1332. The question stem and answer options stay visible for context.

Submitted by kim_seoul· Apr 18, 2026Process

Question

A supplier informs the project manager that producing the quantity of a key component for the project will require an additional month. The project manager has to meet an important milestone in a week. What should the project manager do next?

Options

  • APerform market research to find out if there are other vendors that can produce similar kinds of
  • BSubmit a change request to the change control board (CCB) asking to extend the deadline in
  • CInvolve the legal department, as the vendor is breaching the contract by not delivering the full
  • DAsk the vendor if the minimally sufficient materials can be produced in time to meet the deadline.

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Procurement Management#Risk Response#Problem Solving#Stakeholder Management
Full PMP PracticeBrowse All PMP Questions