PMIPMI
PMP · Question #1316
PMP Question #1316: Real Exam Question with Answer & Explanation
Sign in or unlock PMP to reveal the answer and full explanation for question #1316. The question stem and answer options stay visible for context.
Submitted by jaden.t· Apr 18, 2026Process
Question
A project manager has been managing an agile project for 6 months. Over the last two iterations, the team velocity has decreased due to a new technology that was needed for the product. What should the project manager do to continue with the delivery plan and return to the expected velocity?
Options
- ASeek sponsor approval for additional funding to hire new team members, increasing the capacity
- BReplace poorly performing team members with more experienced members, setting an example
- CUse retrospectives to better understand the new technology's impact on the schedule, map the
- DReevaluate the backlog by looking for high-value/low-effort items, and negotiate a new minimum
Unlock PMP to see the answer
You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Agile Retrospectives#Velocity Management#Continuous Improvement#Problem Solving