PMP · Question #1291

A new agile project is starting. The project manager is asked to confirm the scope to address the concerns of one of the stakeholders. What should the project manager use to explain the project scope?

The correct answer is B. Product backlog. In an agile project, the product backlog serves as the primary, evolving, and prioritized list of all the work to be done, effectively defining the current project scope.

Submitted by neha2k· Apr 18, 2026Process

Question

A new agile project is starting. The project manager is asked to confirm the scope to address the concerns of one of the stakeholders. What should the project manager use to explain the project scope?

Options

  • AUser stories
  • BProduct backlog
  • CProduct roadmap
  • DBusiness requirements document

How the community answered

(29 responses)
  • A
    3% (1)
  • B
    93% (27)
  • C
    3% (1)

Why each option

In an agile project, the product backlog serves as the primary, evolving, and prioritized list of all the work to be done, effectively defining the current project scope.

AUser stories

User stories are individual items within the product backlog, describing specific features from an end-user perspective, but they don't represent the entire project scope on their own.

BProduct backlogCorrect

The product backlog is the definitive source of all requirements and features for an agile project, listed in a prioritized order. It explicitly defines the current scope of the project and is continuously refined, making it the ideal tool to explain what the project encompasses to a stakeholder.

CProduct roadmap

A product roadmap provides a high-level, strategic view of the product's evolution over time, but it lacks the detailed granularity needed to confirm the current project scope.

DBusiness requirements document

Business requirements documents are typically associated with traditional, waterfall methodologies and are less common or comprehensive for scope definition in agile projects, where the product backlog is preferred.

Concept tested: Agile project scope definition (Product Backlog)

Source: https://learn.microsoft.com/en-us/azure/devops/boards/backlogs/understand-backlogs?view=azure-devops

Topics

#Agile Scope Management#Product Backlog#Agile Artifacts