nerdexam
PMIPMI

PMP · Question #1290

PMP Question #1290: Real Exam Question with Answer & Explanation

Sign in or unlock PMP to reveal the answer and full explanation for question #1290. The question stem and answer options stay visible for context.

Submitted by ashley.k· Apr 18, 2026Process

Question

A recently concluded quality audit failed and came back with multiple action items. A newly appointed project manager is reviewing the project status with the team. New stakeholders have been identified, and new audit resources may have to be added to the project. What should the project manager do next?

Options

  • APerform stakeholder engagement.
  • BPerform integrated change control.
  • CUpdate the quality management plan.
  • DUpdate the risk management plan.

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Integrated Change Control#Change Management#Quality Management#Stakeholder Management
Full PMP PracticeBrowse All PMP Questions