PMP · Question #125
A laboratory is launching a new product, defined to be executed in eight iterations with a fixed release date. At the beginning of the second iteration, the project manager realizes that a significant
The correct answer is B. Invite stakeholders to discuss the impact of adding the regulatory feature.. Upon discovering a significant missing regulatory feature in an agile project with a fixed release date, the project manager must immediately invite stakeholders to discuss the impact.
Question
Options
- AAsk the product owner to add the missing feature in the backlog.
- BInvite stakeholders to discuss the impact of adding the regulatory feature.
- CEstimate the related cost and ask for a project extension.
- DIncrease the capacity of the team to include the missed feature.
How the community answered
(32 responses)- A3% (1)
- B81% (26)
- C3% (1)
- D13% (4)
Why each option
Upon discovering a significant missing regulatory feature in an agile project with a fixed release date, the project manager must immediately invite stakeholders to discuss the impact.
Simply adding the feature to the backlog without discussing its impact is insufficient, as it's a significant regulatory item affecting the fixed release date and existing commitments.
Regulatory features are critical and often mandatory, making their omission a significant issue requiring immediate stakeholder engagement. Discussing the impact allows for transparency, collaborative decision-making on how to incorporate it (e.g., de-prioritizing other features, adjusting the timeline, or increasing budget), and ensures alignment on the necessary actions given the fixed release date.
Estimating costs and asking for an extension unilaterally before stakeholder consultation is premature; a collaborative discussion is needed to determine the best path forward.
Increasing team capacity might not be feasible or sufficient, and it's a solution that should only be considered after understanding the full impact and discussing options with stakeholders.
Concept tested: Stakeholder communication for critical scope changes
Topics
Community Discussion
No community discussion yet for this question.