PMI
PMP · Question #1249
The project manager of a high-risk project is concerned about a delay in the schedule that might force the project to move its go-live date. What should the project manager do next?
Sign in or unlock PMP to reveal the answer and full explanation for question #1249. The question stem and answer options stay visible for context.
Submitted by satoshi_tk· Apr 18, 2026Process
Question
The project manager of a high-risk project is concerned about a delay in the schedule that might force the project to move its go-live date. What should the project manager do next?
Options
- ACapture the risk in the risk register and monitor it to prevent it from becoming an issue by taking
- BRaise a change request to the change control board (CCB) to ask for funds to onboard new
- CEnsure that the project meets the committed time lines as this is the core objective and purpose
- DAsk the sponsor to start a new project to support the existing project and help it meet the original
Unlock PMP to see the answer
You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Risk Management#Schedule Management#Risk Identification#Risk Register