PMP · Question #1249
PMP Question #1249: Real Exam Question with Answer & Explanation
The correct answer is A: Capture the risk in the risk register and monitor it to prevent it from becoming an issue by taking. The project manager should first document the identified schedule delay concern as a risk in the risk register and then actively monitor it, implementing risk responses to prevent it from becoming an actual issue. This is a proactive risk management approach.
Question
The project manager of a high-risk project is concerned about a delay in the schedule that might force the project to move its go-live date. What should the project manager do next?
Options
- ACapture the risk in the risk register and monitor it to prevent it from becoming an issue by taking
- BRaise a change request to the change control board (CCB) to ask for funds to onboard new
- CEnsure that the project meets the committed time lines as this is the core objective and purpose
- DAsk the sponsor to start a new project to support the existing project and help it meet the original
Explanation
The project manager should first document the identified schedule delay concern as a risk in the risk register and then actively monitor it, implementing risk responses to prevent it from becoming an actual issue. This is a proactive risk management approach.
Common mistakes.
- B. Raising a change request for funds is a potential risk response, but it's premature before formally identifying, analyzing, and planning a response to the risk in the risk register.
- C. Simply ensuring the project meets timelines is a goal, not an actionable next step when a significant risk like a potential schedule delay is identified; it avoids the necessary risk management process.
- D. Asking the sponsor to start a new project is an extreme and often impractical measure that would only be considered for major, unmanageable issues, not as a first step for an identified risk.
Concept tested. Proactive risk identification and management
Reference. https://www.pmi.org/pmbok-guide-standards/foundational/pmbok/risk-management
Topics
Community Discussion
No community discussion yet for this question.