PMIPMI
PMP · Question #1222
PMP Question #1222: Real Exam Question with Answer & Explanation
Sign in or unlock PMP to reveal the answer and full explanation for question #1222. The question stem and answer options stay visible for context.
Submitted by layla.eg· Apr 18, 2026Process
Question
A customer requests additional changes 1 day before the planned change date. How should the project manager respond to the change request?
Options
- AReject the changes as the lead time is too short.
- BCheck if the changes are covered in the statement of work (SOW).
- CDetermine whether the project team is capable of making the changes.
- DReview the additional changes and perform integrated change control.
Unlock PMP to see the answer
You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Change Management#Integrated Change Control#Change Request Process#Project Controls