nerdexam
PMIPMI

PMP · Question #1188

PMP Question #1188: Real Exam Question with Answer & Explanation

Sign in or unlock PMP to reveal the answer and full explanation for question #1188. The question stem and answer options stay visible for context.

Submitted by mateo_ar· Apr 18, 2026Process

Question

A new manufacturing line project is planned to be delivered in iterations for the equipment installation phase. During one of the iterations, the vendor communicates to the project manager that they will not be able to deliver some of the equipment at the agreed dates. What should the project manager do next?

Options

  • AFind another vendor who can fulfill the delivery dates.
  • BReplan the remaining iterations according to the new installation dates.
  • CUpdate the product backlog in order to address the delays.
  • DReview the procurement agreements to address the situation.

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Procurement Management#Contract Management#Vendor Management#Issue Resolution
Full PMP PracticeBrowse All PMP Questions