nerdexam
PMI

PMP · Question #1177

PMP Question #1177: Real Exam Question with Answer & Explanation

Sign in or unlock PMP to reveal the answer and full explanation for question #1177. The question stem and answer options stay visible for context.

Submitted by kavita_s· Apr 18, 2026Process

Question

A project manager notices that the project team is unlikely to complete the development of a system on time before the testing start date, which was based on the technical complexity of the project. What should the project manager do before communicating with the client during the regular project progress meeting?

Options

  • AAsk the project sponsor to inform the client in the next update.
  • BDo not disclose the likelihood of a delay as it is yet to happen.
  • CWork with the project team to evaluate the potential delay.
  • DTell the client about the chance for the potential delay.

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Risk Management#Stakeholder Communication#Team Collaboration#Issue Resolution
Full PMP Practice
A project manager notices that the project team is unlikely to... | PMP Q#1177 Answer | NerdExam