nerdexam
PMIPMI

PMP · Question #1164

PMP Question #1164: Real Exam Question with Answer & Explanation

Sign in or unlock PMP to reveal the answer and full explanation for question #1164. The question stem and answer options stay visible for context.

Submitted by klara.se· Apr 18, 2026Process

Question

A project manager is using a hybrid approach for a project. The project team created and reviewed the risk log with the stakeholders at the beginning of the project. However, midway through the project, the project team and stakeholders became misaligned with the risks and mitigation strategies. When should the risks be reviewed to ensure alignment between the project team and the stakeholders?

Options

  • ADuring each steering committee meeting
  • BDuring the retrospectives
  • CDuring the risk register update
  • DDuring each iteration and review

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Risk Management#Hybrid Project Management#Iterative Reviews#Stakeholder Alignment
Full PMP PracticeBrowse All PMP Questions