PMP · Question #1150
PMP Question #1150: Real Exam Question with Answer & Explanation
The correct answer is B: Finish to start. During planning, the project team identified a missing dependency: the product must be tested before it can be released to the customer. This sequential relationship needs to be accurately represented in the schedule.
Question
A project team is in the planning stage and has prepared a list of activities and completed sequencing the activities. During a review, the team noted that there is a dependency missing between: - Test the product - Release to customer According to the quality management plan, the product must be tested before being released. How should the project manager enter this dependency?
Options
- AStart to start
- BFinish to start
- CFinish to finish
- DStart to finish
Explanation
During planning, the project team identified a missing dependency: the product must be tested before it can be released to the customer. This sequential relationship needs to be accurately represented in the schedule.
Common mistakes.
- A. Start-to-Start (SS) means the successor activity can start when the predecessor activity starts, which does not ensure that testing is finished before the release begins.
- C. Finish-to-Finish (FF) means the successor activity can finish when the predecessor activity finishes, which would allow the release to start long before testing is complete.
- D. Start-to-Finish (SF) means the successor activity cannot finish until the predecessor activity starts, a rarely used dependency type that does not fit the requirement of testing completing before release.
Concept tested. Activity sequencing and dependency types
Reference. https://learn.microsoft.com/en-us/project/link-tasks-in-a-project-fs-ss-ff-sf
Topics
Community Discussion
No community discussion yet for this question.