nerdexam
PMIPMI

PMP · Question #1143

PMP Question #1143: Real Exam Question with Answer & Explanation

Sign in or unlock PMP to reveal the answer and full explanation for question #1143. The question stem and answer options stay visible for context.

Submitted by takeshi77· Apr 18, 2026Process

Question

In an agile project, the team planned to complete 40 story points in an iteration, but only completed 30 story points. What is the schedule performance index (SPI)?

Options

  • A30/40
  • B30/70
  • C40/30
  • D40/70

Unlock PMP to see the answer

You've previewed enough free PMP questions. Unlock PMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Agile metrics#Schedule Performance Index (SPI)#Story points#Performance measurement
Full PMP PracticeBrowse All PMP Questions